Little Creek Outfall Improvement Project

The project includes the installation of approximately 12,694 LF of gravity sewer to upsize existing undersized pipes. The lines will consist of approximately 172 LF of 8″, 6,130 LF of 30″ and 6,392 of 36″ gravity sewer pipe. The project also includes an additional siphon at the Muddy Creek crossing. The project will begin at the intersection of the Little Creek Outfall and the Muddy Creek Outfall north of Stratford Road and ends west of Burlwood Drive in Winston-Salem.

Work Currently In Progress:

Notice to proceed with construction was issued Jan 9 2017. The construction time is 365 days.